Scrum PSPO I Exam Page 9 (Dumps)
Question No:-41
|
What does Cone of Uncertainty show?
1. How much work remains till the end of the Sprint
2. How much is known about the Product over time
3. Dependencies, start times and stop times for project tasks
4. Hierarchy of tasks that comprise a project
Answer:-2. How much is known about the Product over time
For Note:-
The Cone of Uncertainty describes the evolution of the amount of uncertainty during a project.
|
|
Question No:-42
|
What is the essence of Scrum? Select the most appropriate option.
1. The Development Team
2. The Scrum Master and the Product Owner
3. A small team of people that is highly flexible and adaptive
4. The Scrum Guide
Answer:-3. A small team of people that is highly flexible and adaptive
For Note:-
The essence of Scrum is a small team of people. The individual team is highly flexible and adaptive. These strengths continue operating in single, several, many, and networks of teams that develop, release, operate and sustain the work and work products of thousands of people. They collaborate and interoperate through sophisticated development architectures and target release environments.
|
|
Question No:-43
|
What technique should be used for representing Product Backlog Items?
1. Acceptance Tests
2. Use Cases
3. Scenarios
4. Any technique, even a mix of several techniques
5. User Stories
Answer:-4. Any technique, even a mix of several techniques
For Note:-
User stories are a fairly common technique for representing Product Backlog Items, but other techniques can be used instead. For instance, a team can use scenarios, use cases, acceptance tests, etc. The Product Backlog might even contain a heterogeneous mix of the above.
The Product Owner should work with the rest of the Scrum Team on choosing and optimizing the techniques used to represent Product Backlog Items.
|
|
Question No:-44
|
Who is allowed to make changes in the Product Backlog? Select two options.
1. Anyone
2. The Key Stakeholders
3. The Product Owner
4. The Development Team, but with permission of the Product Owner
5. The Scrum Master
Answer:-(3) and (4)
For Note:-
The Product Owner is the sole person responsible for the Product Backlog. However, he or she can delegate some work related to product backlog management to the Development Team.
|
|
Question No:-45
|
What is the Sprint Backlog?
1. The Product Backlog items selected for this Sprint plus the plan for delivering them
2. The Product Backlog items selected for this Sprint
3. The Product Backlog items selected for this Sprint plus the Team Backlog items
4. The plan for delivering Product Backlog items
Answer:-1. The Product Backlog items selected for this Sprint plus the plan for delivering them
For Note:-
The Sprint Backlog is the set of Product Backlog items selected for the Sprint, plus a plan for delivering the product Increment and realizing the Sprint Goal.
|
|
|