Scrum PSPO I Exam Page 12 (Dumps)
Question No:-56
|
What are the time-boxes for the Sprint Review and the Sprint Retrospective?
1. 4 and 3 hours respectively
2. 3 and 4 hours respectively
3. 4 hour time-box for each
4. 3 hour time-box for each
Answer:-1. 4 and 3 hours respectively
For Note:-
The Sprint Review is at most a four-hour meeting for one-month Sprints.
The Sprint Retrospective is at most a three-hour meeting for one-month Sprints.
|
|
Question No:-57
|
What is the Increment?
1. The sum of all the Product Backlog items completed during the Sprint
2. The sum of all the Product Backlog items completed during the Sprint and the value of the increments of all previous Sprints
3. All "Done" items in the Sprint Backlog
4. All items in the Sprint Backlog that could be released regardless of whether the Product Owner decides to actually do it
Answer:-(3),(4) and (5)
For Note:-
A Product Backlog is never complete. The earliest development of it only lays out the initially known and best-understood requirements. The Product Backlog evolves as the product and the environment in which it will be used evolves. The Product Backlog is dynamic; it constantly changes to identify what the product needs to be appropriate, competitive, and useful. As long as a product exists, its Product Backlog also exists.
|
|
Question No:-58
|
The Product Owner should be expertly aware of the marketplace for the product.
1. False
2. It depends
3. True
Answer:-3. True
For Note:-
The Product Owner should be expertly aware of the marketplace for the product. They should constantly be gathering and re-gathering information and data regarding the marketplace, so that the product value is maximized. Getting out of touch with the marketplace can be a recipe for product disaster.
|
|
Question No:-59
|
Who is responsible for creation of the Definition of “Done”?
1. The Development Team
2. The Scrum Team
3. The Scrum Master
4. The Product Owner
Answer:-1. The Development Team
For Note:-
If the definition of “done” for an increment is part of the conventions, standards or guidelines of the development organization, all Scrum Teams must follow it as a minimum. If “done” for an increment is not a convention of the development organization, the Development Team of the Scrum Team must define a definition of “done” appropriate for the product. If there are multiple Scrum Teams working on the system or product release, the development teams on all of the Scrum Teams must mutually define the definition of “Done.”
|
|
Question No:-60
|
Once the Product Owner gained his Product Vision and defined the tactics of bringing this vision to life, it is a bad idea to change them before the next Product Release.
1. True
2. False
Answer:-2. False
For Note:-
The PO should never be afraid to change the vision or tactics based on marketplace changes. Being able to strategically re-pivot and capture value in new and different ways is one of the key benefits of an Agile mindset.
|
|
|