Question No:-51

A Development Team is waiting for a specific software component that they need to integrate and use.

The component should be ready in a month.

The Backlog Items with highest priorities depend on this specific component.

What should the Product Owner do?


  1. Transfer the dependent Items to the Integration Team
  2. Remove the dependent Items from the Product Backlog and put them in a special wait list. When the dependency is resolved, the Items should be returned back.
  3. Nothing. The Product Backlog already has the most valuable items at the top. The Development Team cannot proceed further until the dependency is resolved.
  4. Make sure the dependency is visible in the Product Backlog and the Development Team has enough independent Items for the next Sprint.

 






Question No:-52

What is the Increment?


  1. The sum of all the Product Backlog items completed during the Sprint
  2. The sum of all the Product Backlog items completed during the Sprint and the value of the increments of all previous Sprints
  3. All "Done" items in the Sprint Backlog
  4. All items in the Sprint Backlog that could be released regardless of whether the Product Owner decides to actually do it

 





Question No:-53

Where Scrum can be used? Check all the applicable items.


  1. Development of almost everything we use in our daily lives as individuals and societies
  2. Development of products and enhancements
  3. Development of software and hardware
  4. Managing the operation of an organization
  5. Development and sustaining of Cloud and other operational environments
  6. Research and identifying of viable markets, technologies, and product capabilities

 





Question No:-54

What does the word “development” mean in the context of Scrum? Select the best option.


  1. Research and identifying of viable markets, technologies, and Product capabilities
  2. Development of an operational environment for the Product
  3. Complex work that can include all the suggested options and even more
  4. Product development, its releasing and sustaining
  5. Software and hardware development

 









Question No:-55

What two attributes are optional for a Product Backlog Item?


  1. Value
  2. Order
  3. Estimate
  4. Test descriptions that will prove PB Item completeness when "Done"
  5. Description
  6. Dependencies

 