Scrum PSPO I Exam Page 11 (Dumps)
Question No:-51
|
A Development Team is waiting for a specific software component that they need to integrate and use.
The component should be ready in a month.
The Backlog Items with highest priorities depend on this specific component.
What should the Product Owner do?
1. Transfer the dependent Items to the Integration Team
2. Remove the dependent Items from the Product Backlog and put them in a special wait list. When the dependency is resolved, the Items should be returned back.
3. Nothing. The Product Backlog already has the most valuable items at the top. The Development Team cannot proceed further until the dependency is resolved.
4. Make sure the dependency is visible in the Product Backlog and the Development Team has enough independent Items for the next Sprint.
Answer:-4. Make sure the dependency is visible in the Product Backlog and the Development Team has enough independent Items for the next Sprint.
For Note:-
The Product Backlog should make the dependency visible to all the interested parties.
Usually Items with external dependencies are not considered “Ready” for selection at the Sprint Planning.
Development Teams should deliver an Increment of product functionality every Sprint.
|
|
Question No:-52
|
What is the Increment?
1. The sum of all the Product Backlog items completed during the Sprint
2. The sum of all the Product Backlog items completed during the Sprint and the value of the increments of all previous Sprints
3. All "Done" items in the Sprint Backlog
4. All items in the Sprint Backlog that could be released regardless of whether the Product Owner decides to actually do it
Answer:-2. The sum of all the Product Backlog items completed during the Sprint and the value of the increments of all previous Sprints
For Note:-
The Increment is the sum of all the Product Backlog items completed during the Sprint and the value of the increments of all previous Sprints.
|
|
Question No:-53
|
Where Scrum can be used? Check all the applicable items.
1. Development of almost everything we use in our daily lives as individuals and societies
2. Development of products and enhancements
3. Development of software and hardware
4. Managing the operation of an organization
5. Development and sustaining of Cloud and other operational environments
6. Research and identifying of viable markets, technologies, and product capabilities
Answer:-(1),(2),(3),(4),(5) and (6)
For Note:-
Scrum has been used to develop software, hardware, embedded software, networks of interacting function, autonomous vehicles, schools, government, marketing, managing the operation of organizations and almost everything we use in our daily lives, as individuals and societies.
Scrum has been used extensively, worldwide, to:
Research and identify viable markets, technologies, and product capabilities;
Develop products and enhancements;
Release products and enhancements, as frequently as many times per day;
Develop and sustain Cloud (online, secure, on-demand) and other operational environments for product use; and,
Sustain and renew products.
|
|
Question No:-54
|
What does the word “development” mean in the context of Scrum? Select the best option.
1. Research and identifying of viable markets, technologies, and Product capabilities
2. Development of an operational environment for the Product
3. Complex work that can include all the suggested options and even more
4. Product development, its releasing and sustaining
5. Software and hardware development
Answer:-3. Complex work that can include all the suggested options and even more
For Note:-
When the words “develop” and “development” are used in the Scrum Guide, they refer to complex work including software and hardware development, development and releasing of products and enhancements, development and sustaining product operational environments, research and identifying of viable markets and technologies, and even more.
|
|
Question No:-55
|
What two attributes are optional for a Product Backlog Item?
1. Value
2. Order
3. Estimate
4. Test descriptions that will prove PB Item completeness when "Done"
5. Description
6. Dependencies
Answer:-(4) and (6)
For Note:-
Product Backlog items have the attributes of a description, order, estimate, and value. Product Backlog items often include test descriptions that will prove its completeness when “Done”.
|
|
|