Question No:-11
|
Which of the following statements is one of the five Lean Thinking principles?
Choose the correct option from below list
1. Customer collaboration over contract negotiation
2. Identify the Value Stream for each product
3. Deliver working software frequently
4. Decentralize decision-making
Answer:-2. Identify the Value Stream for each product
|
|
Question No:-12
|
When should Agile Teams make time for innovation?
Choose the correct option from below list
1. Continuously throughout the PI
2. During the Innovation and Planning Iteration
3. When there are Enabler Stories in the Backlog
4. At a consistent time each day during the Iteration
Answer:-2. During the Innovation and Planning Iteration
|
|
Question No:-13
|
What is one method for designing the end-to-end Customer experience?
Choose the correct option from below list
1. Persona development
2. Feature storming
3. Journey mapping
4. Whole-product thinking
Answer:-3. Journey mapping
|
|
Question No:-14
|
Which of the following roles has content authority for the ART Backlog?
Choose the correct option from below list
1. System Architect
2. Business Owner
3. Product Owner
4. Product Management
Answer:-4. Product Management
|
|
Question No:-15
|
What is one benefit of capacity allocation?
Choose the correct option from below list
1. It ensures all Value Streams in the Portfolio are appropriately funded
2. It prevents different types of backlog items from being compared against each another
3. It enables effective time-tracking
4. It allocates developers and testers to an initiative
Answer:-2. It prevents different types of backlog items from being compared against each another
|
|
Question No:-16
|
Why is it important to establish a definition of done?
Choose the correct option from below list
1. To create alignment on when Stories are complete
2. To enable Scrum Masters/Team Coaches to enforce quality
3. To create standardized work between all Agile Teams
4. To ensure Features provide the expected business benefits
Answer:-1. To create alignment on when Stories are complete
|
|
Question No:-17
|
What is one way Kanban boards are used in SAFe?
Choose the correct option from below list
1. To manage WIP limits
2. To manage runway cadence
3. To manage non-functional requirements (NFRs) in the backlog
4. To manage PI Objectives
Answer:-1. To manage WIP limits
|
|
Question No:-18
|
How often does the Innovation and Planning (IP) Iteration occur?
Choose the correct option from below list
1. Every two PIs
2. Every two Iterations
3. Once per year
4. During every PI
Answer:-4. During every PI
|
|
Question No:-19
|
What is the next action for improvement items identified during the Iteration Retrospective?
Choose the correct option from below list
1. They are given to the Scrum Master/Team Coach who resolves them
2. They are entered as Stories in the Team Backlog
3. They are escalated to the Business Owners
4. They are ROAMed with the rest of the risks
2. They are entered as Stories in the Team Backlog
|
|
Question No:-20
|
What is one tool that visualizes Features representing a workflow?
Choose the correct option from below list
1. Story Maps
2. Team Kanban
3. Continuous Delivery Pipeline
4. User Experience Design
|
|