SAFe 5 DevOps Practitioner
Question No:-37
|
Which steps in the Value Stream should be the main focus when prioritizing improvement items?
Choose the correct option from below list
(1)Steps with a long process time
(2)Steps with long lead time and short process time in the current-state map
(3)Steps with a high activity ratio
(4)Steps with short process time and short lead time in the future-state map
Answer:-(2)Steps with long lead time and short process time in the current-state map
|
|
Question No:-38
|
What should be measured in a CALMR approach to DevOps?
Choose the correct option from below list
(1)Everything
(2)Mean time to restore
(3)Flow, quality, and value
(4)Deployment frequency
|
Question No:-39
|
How is Lean UX used in Continuous Exploration?
Choose the correct option from below list
(1)To automate the user interface scripts
(2)To create a platform to continuously explore
(3)To collaboratively create a benefit hypothesis
(4)To validate the return on investment
Answer:-(3)To collaboratively create a benefit hypothesis
|
|
Question No:-40
|
Continuous Deployment enables which key business objective?
Choose the correct option from below list
(1)Manage technical debt
(2)Release continuously
(3)Time-to-market
(4)Business value
Answer:-(3)Time-to-market
|
|
Question No:-41
|
What are two parts of the Continuous Delivery Pipeline? (Choose two.)
Choose the correct option from below list
(1)Continuous Exploration
(2)Continuous Experimentation
(3)Continuous Integration
(4)Continuous Security
(5)Continuous Delivery
|
Question No:-42
|
What is the desired frequency of deployment in SAFe?
Choose the correct option from below list
(1)Continuous
(2)Daily
(3)Once per Iteration
(4)Once per PI
|
Question No:-43
|
After the team maps the steps of the current state Value Stream during value stream mapping, what are the next two steps? (Choose two.)
Choose the correct option from below list
(1)Identify who is involved in each step
(2)Create a future state value stream map
(3)Perform a SWOT analysis
(4)Calculate the Activity Ratio
(5)Measure the performance at each step
Answer:-(5)Measure the performance at each step
|
|
Question No:-44
|
What are two aspects of the Continuous Delivery Pipeline, in addition to Continuous Integration? (Choose two.)
Choose the correct option from below list
(1)Continuous Release
(2)Continuous Deployment
(3)Continuous Improvement
(4)Continuous Exploration
(5)Continuous Testing
|
Question No:-45
|
What is an output of the Release activity?
Choose the correct option from below list
(1)A Feature migrated to the cloud
(2)A Feature deployed to production
(3)A Feature made available to end users
(4)A Feature made available to internal users
|
Question No:-46
|
Gemba walks are an important competency in support of which activity of the DevOps Health Radar?
Choose the correct option from below list
(1)Continuous Exploration
(2)Collaborate and Research
(3)Learn
(4)Hypothesize
|
Question No:-47
|
Who is responsible for building and continually improving the Continuous Delivery Pipeline?
Choose the correct option from below list
(1)System Teams
(2)Agile Release Trains
(3)Scrum Teams
(4)DevOps Teams
|
Question No:-48
|
DevOps is a key enabler of continuous delivery.
What does continuous mean in this context?
Choose the correct option from below list
(1)To deploy to production and release on cadence every Iteration
(2)To deploy to production and release at least once every Program increment
(3)To deploy to production as often as possible and release when the business needs it
(4)To deploy to production multiple times per year and release on a cadence once or twice a year
|
|
|
|
|
|
|
|
|