Question No:-11

According to the values of Scrum, which is the best way to create Development Teams?


  1. The Product Owner will create a skills matrix according to what is needed for the project and work with the technical leads to allocate resources to the team.
  2. Work with the leadership team to allocate members according to skills, seniority and experience to ensure that all Development Teams are balanced fairly.
  3. Provide boundaries to the developers and allow them to self-organize into Development Teams.

 




Question No:-12

When multiple Scrum Teams are working from the same Product Backlog, also known as scaled Scrum, they must still work in conformance of the Scrum guide.


  1. True
  2. False

 




Question No:-13

In Scrum, how would budgeting and financial forecasting be performed? (Choose two.)


  1. Frequently inspect the outcomes of the delivered Sprint Increments to understand how much value is being produced per investment spent.
  2. A single release may be funded with several Sprints where every Sprint is producing shippable increments.
  3. Budgeting is not necessary as the only funding necessary is the operational costs of the Scrum Teams.
  4. Fixed budgets are not allowed in Scrum.

 




Question No:-14

Steven is a Scrum Master that was hired to help an organization, that is new to Scrum, understands and enacts Scrum effectively.

Which three activities would be acceptable? (Choose three.)


  1. Require all teams in the organization to start using Scrum as soon as possible.
  2. Arrange 1:1 coaching sessions to discuss any identified concerns Steven may have.
  3. Schedule formal trainings.
  4. Penalize any Scrum Team members who are not staying within the Scrum Framework.
  5. Educate stakeholders and clients about Scrum.
  6. Extend Retrospectives to include formal training.

 




Question No:-15

A Scrum Team has been working on a product for several iterations and has an average velocity of 55 units of 'done' work per Sprint. A second team will be added to work on the same product.

What might be the impact on the original team?


  1. Their velocity is likely not affected and will remain at 55.
  2. Their velocity is likely to drop and be less than 55.
  3. Their velocity is likely to rise and be more than 55.

 