Question No:-61

A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.

What should the team do?


  1. Estimate only functional requirements that will impact product quality
  2. Add team resources
  3. Refer the issue to the product owner
  4. Break non-functional requirements into those that can be delivered in the given sprint

 






Question No:-62

A development team and product owner disagrees on a user story in the product backlog.

What should the agile practitioner do?


  1. Have the development team follow the product owner's direction
  2. Openly challenge the product owner in the effort to poke holes in their approach
  3. Facilitate a conversation about the user story between the development team and the product owner
  4. Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner

 





Question No:-63

During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points.

How should this be handled?


  1. The story should be assigned eight story points as per the majority vote
  2. The story should be added to the backlog and reassessed later
  3. The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached
  4. The decision for the number of story points should be made by the customer

 





Question No:-64

A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge.

What should the agile practitioner do?


  1. Select and implement collaboration tools to augment team interactions
  2. Provide each geographical area with their own product owner and divide the work between the teams
  3. Increase the number of requirements documents and ensure they are clearly communicated
  4. After several sprints, calculate velocity based on primary team location and use secondary team as reserve

 





Question No:-65

Team A is working on the second sprint of a product release. Team B, which is an interdependent team located on the same floor, requires exclusive and frequent information to complete its sprint goal.

What should the agile team do?



  1. Create a central repository for information, and provide access to team B
  2. Use an information board that will be visible to all passing through the workspace
  3. Email all stakeholders with status updates
  4. Provide team B with the information on an ג€as neededג€ basis
 









Question No:-66

Chart Base on the burn down chart, what is the iteration's status?


  1. It trended ahead of scheduled and completed everything on time
  2. It took more time than expected and had to be lengthened
  3. It trended behind schedule and did not complete everything on time
  4. It took less time than expected and had to be shortened

 





Question No:-67

During planning sessions, an agile practitioner notices that some team members do not share common ideas.

What should the agile practitioner do?


  1. Ask the team if they would like to adopt alternative techniques
  2. Create a team norms document to set particular guidelines
  3. Ask the scrum master to resolve the issue at the stand up meeting
  4. Capture feedback during lessons learned at the end of the iteration
 





Question No:-68

More details for a story are required before the upcoming sprint planning meeting.

What should the scrum master do?


  1. Email the product owner requesting detailed story specifications and wait for a response
  2. Gather the details from the team members before sprint planning
  3. Schedule a story grooming session with the product owner before sprint planning
  4. Conduct a planning poker session with the team

 





Question No:-69

Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retrospective.

What should the agile practitioner do?


  1. Review established ground rules with the team
  2. Ask team members specific questions to identify the cause
  3. Encourage the team to continue working to maintain the iteration's schedule
  4. Meet with the product owner and stakeholders to discuss the issue

 





Question No:-70

A company is considering developing a new, complex application that will require a large initial investment. However, if successful, the profit potential is high.

When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?


  1. Calculated planned percent complete (PPC)
  2. Many small minimally marketable features (MMFs)
  3. Story points rather than cost estimates
  4. Calculated earned value (EV)

 