| Difference between Burn Down and Burn UP Charts?
Both of these charts are used by Project Manager to communicate and track progress of their projects. And these charts are widely used in Agile and scrum software project management.
(1)Burn Down:-This charts shows how much work is remaining to be done in the project. This charts shows that the team did not accomplish much in the middle of the project but heroically finished everything at the end.
(2)Burn UP:-This charts shows that how much work has been completed and also shows the toal amount of work. This charts will shows the complete picture and the scope increased at the begining of the project and some scope was removed to finish the project by the deadline. And here Team made some stedy progress through the entire duration of project. | | |