Lean Six Sigma Yellow Belt Page 1 (Dumps)
Question No:-1
|
When a process has proven itself to function at a Six Sigma level this means there are less than ________ defects per million opportunities.
1. 1.7
2. 2.6
3. 3.4
4. 10
|
Question No:-2
|
Six Sigma refers to a process whose output has at least 95% of its data points within 6 Standard Deviations from the Mean.
1. True
2. False
|
Question No:-3
|
Training cost is $3,000 and a project required an initial investment of $12,000. If the project yields monthly savings of $1,800 beginning after 3 months, what is the payback period in months (before money costs and taxes)?
1. 4.17
2. 8.33
3. 11.33
4. 28.28
|
Question No:-4
|
The ROI for a project is a measurement metric that stands for Return on Investment and is one of the methods used to measure the success of a Lean Six Sigma project.
1. True
2. False
|
Question No:-5
|
The DMAIC approach to problem solving stands for Define, __________, Analyze, Improve and Control.
1. Manage
2. Measure
3. Memorize
4. Manipulate
|
Question No:-6
|
Voice of the Customer is a Lean Six Sigma technique to determine the ___________ attributes of a product or service.
1. Desirable
2. Beneficial
3. Critical-to-Quality
4. Preferred
Answer:-3. Critical-to-Quality
|
|
Question No:-7
|
Benefits and working conditions would be primarily the concern of which of the following?
1. Voice of the Customer
2. Voice of the Employee
3. Voice of the Business
4. Voice of the Process
Answer:-2. Voice of the Employee
|
|
Question No:-8
|
In the expression Y = f(Xn) Y, the output, is the ___________ variable and Xn, the inputs, are the __________ variables.
1. Independent, dependent
2. Individual, multiple
3. Sole, multiple
4. Dependent, independent
Answer:-4. Dependent, independent
|
|
Question No:-9
|
When we assess the Voice of the Customer we are attempting to determine the gaps in our processes between `what is` and __________________.
1. ג€What isn'tג€
2. ג€What will make moneyג€
3. ג€What will cost lessג€
4. ג€What should beג€
Answer:-4. ג€What should beג€
|
|
Question No:-10
|
Which of the following would likely not be a CTQ (Critical-to-Quality) for the purchase of a product?
1. Functionality
2. Durability
3. Dependability
4. None
|
|