Scrum PSPO I Exam Page 6 (Dumps)
Question No:-26
|
What happens when a Sprint is cancelled? Select three.
1. All incomplete Product Backlog Items are re-estimated and put back on the Product Backlog
2. Several top Product Backlog Items are taken into the Sprint Backlog to replace the obsolete items
3. If part of the work is potentially releasable, the Product Owner typically accepts it
4. At the Sprint Retrospective the Scrum Master determines who from the Development Team is responsible for cancelling the Sprint
5. Any completed and “Done” Product Backlog items are reviewed
Answer:-(1), (3) and (5)
For Note:-
When a Sprint is cancelled, any completed and “Done” Product Backlog items are reviewed. If part of the work is potentially releasable, the Product Owner typically accepts it. All incomplete Product Backlog Items are re-estimated and put back on the Product Backlog.
|
|
Question No:-27
|
Who participates in the Sprint Planning? Select three.
1. The Product Owner
2. The Scrum Master
3. The Key Stakeholders
4. The Team Manager
5. The Development Team
Answer:-(1), (2) and (5)
For Note:-
The work to be performed in the Sprint is planned at the Sprint Planning. This plan is created by the collaborative work of the entire Scrum Team.
|
|
Question No:-28
|
Product Backlog Refinement practice focuses on Items for upcoming Sprints, not the current Sprint in progress. True or false?
1. True
2. False
Answer:-1. True
For Note:-
True. Product Backlog refinement is the act of adding detail, estimates, and order to items in the Product Backlog. The Items in the current Sprint are no longer on the Product Backlog, because they are now on the Sprint Backlog.
|
|
Question No:-29
|
Who is responsible for crafting the Sprint Goal at the Sprint Planning?
1. The Product Owner
2. The Scrum Team
3. The Development Team
4. The Key Stakeholders
5. The Scrum Master
Answer:-2. The Scrum Team
For Note:-
After the Development Team forecasts the Product Backlog items it will deliver in the Sprint, the Scrum Team crafts a Sprint Goal.
|
|
Question No:-30
|
Who participates in the Sprint Review? Select all applicable variants.
1. The Key Stakeholders
2. The Development Team
3. The Organization CEO
4. The Product Owner
5. The Scrum Master
Answer:-(1),(2),(4) and (5)
For Note:-
During the Sprint Review, the Scrum Team and stakeholders collaborate about what was done in the Sprint. Based on that and any changes to the Product Backlog during the Sprint, attendees collaborate on the next things that could be done to optimize value.
|
|
|