Question No:-1
|
During the PI Planning event, when are planning adjustments agreed upon?
1. During breakout sessions
2. During the draft plan review
3. During the management review and problem-solving
4. During Scrum of scrums
Answer:-3. During the management review and problem-solving
|
|
Question No:-2
|
Which role serves as the servant leader for the Agile Release Train?
1. Business Owner
2. Release Train Engineer
3. Agile Coach
4. Scrum Master
Answer:-2. Release Train Engineer
|
|
Question No:-3
|
Which statement is true about ART events?
1. ART events run inside the team events, and the team events create a closed-loop system
2. Team events run inside the ART events, and the ART events create a closed-loop system
3. The Inspect and Adapt is the only ART event required to create a closed-loop system
4. The daily stand-up is an ART event that requires the scrum of scrums and Program Owner sync involvement in the closed-loop system
Answer:-2. Team events run inside the ART events, and the ART events create a closed-loop system
|
|
Question No:-4
|
According to SAFe Principle #10, what should the Enterprise do when markets and customers demand change?
1. Create an Agile Release Train to focus on value
2. Reorganize the network around the new value flow
3. Apply development cadence and synchronization to operate effectively and manage uncertainty
4. Create a reliable decision-making framework to empower employees and ensure a fast flow of value
Answer:-2. Reorganize the network around the new value flow
|
|
Question No:-5
|
What is part of the role of the Scrum Master?
1. To escalate ART impediments
2. To prioritize and identify what is ready for Iteration Planning
3. To facilitate all team events
4. To coach the interactions with the Scrum Framework
Answer:-3. To facilitate all team events
|
|
Question No:-6
|
Which statement is a value from the Agile Manifesto?
1. Customer collaboration over following a plan
2. Customer collaboration over a constant indefinite pace
3. Individuals and interactions over contract negotiation
4. Individuals and interactions over processes and tools
Answer:-1. Customer collaboration over following a plan
Most of the people answer (2) as option
|
|
Question No:-7
|
Which core competency of the Lean Enterprise helps drive Built-in Quality practices?
1. DevOps and Release on Demand
2. Team and Technical Agility
3. Business Solutions and Lean Systems Engineering
4. Lean Portfolio Management
Answer:-2. Team and Technical Agility
|
|
Question No:-8
|
The primary need for SAFe is to scale the idea of what?
1. Organizational and Functional Alignment
2. Business Agility
3. Technical Solution Delivery
4. Lean Portfolio Management
Answer:-2. Business Agility
|
|
Question No:-9
|
What is one way Lean-Agile leaders lead by example?
1. By modeling SAFe’s Lean-Agile Mindset, values, principles, and practices
2. By using the SAFe Implementation Roadmap to script the way for change
3. By mastering the Seven Core Competencies of the Lean Enterprise
4. By applying empathic design and focusing on Customer Centricity
1. By modeling SAFe’s Lean-Agile Mindset, values, principles, and practices
|
|
Question No:-10
|
SAFe’s first Lean-Agile Principle includes “Deliver early and often” and what else?
1. Apply systems thinking
2. Decentralize decision-making
3. Deliver value incrementally
4. Apply cadence
Answer:-3. Deliver value incrementally
|
|
|