Question No:-1
|
What does the Six Sigma mean?
1. ultimately reduces process costs
2. decreases customer satisfaction
3. is a methodology for process improvement
4. is a statistical concept that seeks to find variation in processes
5. all of the above
Answer:-3. is a methodology for process improvement
|
|
Question No:-2
|
What do Data driven processes mean?
1. are heavily based on intuition
2. rely heavily on the experience of the process owners
3. are based on statistical data, measurement and metrics
4. do NOT rely on mathematical models
Answer:-3. are based on statistical data, measurement and metrics
|
|
Question No:-3
|
Beta testing is the act of implementing a new idea, system or product on a large scale, controlled environment within the entire organization.
1. True
2. False
|
Question No:-4
|
A process that performs at a 6 sigma level:
1. is considered statistically 'perfect'
2. has 3.4 defects per million opportunities
3. operates at a 99.99966% accuracy
4. all of the above
Answer:-4. all of the above
|
|
Question No:-5
|
The statistical difference between a process operating at a 5 sigma level and a process operating at a 6 sigma level is markedly different when it comes to the number of defects present.
1. True
2. False
|
Question No:-6
|
A Six Sigma level is calculated by which of the following equations:
1. (Opportunities - Defects)/Opportunities x 100
2. (Opportunities + Defects)/Opportunities x 100
3. (Defects - Opportunities)/Defects x 100
4. (Defects + Opportunities)/Defects x 100
Answer:-1. (Opportunities - Defects)/Opportunities x 100
|
|
Question No:-7
|
When prioritizing Six Sigma projects within an organization:
1. The project with the statistically lowest sigma level should always be prioritized
2. The project with the highest potential cost savings should always be prioritized.
3. The project with the highest potential customer satisfaction increase should always be prioritized.
4. All of the above should be considered and statistically researched before choosing the best option for the organization at hand.
Answer:-4. All of the above should be considered and statistically researched before choosing the best option for the organization at hand.
|
|
Question No:-8
|
What does the Value Stream mean?
1. is the sequence of all items, events and people required to produce an end result.
2. is used to identify areas of concern, waste and improvement.
3. Neither A nor B
4. Both A and B
|
Question No:-9
|
An organization that fully adopts the Six Sigma methodology:
1. completes a few Six Sigma Projects and reaps the financial benefits
2. continuously measures and improves processes indefinitely
3. improves upon a few processes then moves on
4. identifies and prioritizes areas of opportunity once or twice a year
Answer:-2. continuously measures and improves processes indefinitely
|
|
Question No:-10
|
Which of the following is NOT an example of a common challenge of the Six Sigma Methodology within an organization?
1. lack of support
2. poor project execution
3. excess resources
4. lack of access to data
Answer:-3. excess resources
|
|
|